Commissioning DNT2Mi

6.1

Automatic power-up test

DN01145897
Issue 2-0 en
This chapter describes the most common items that need to be checked before
DNT2Mi is taken into use.
DNT2Mi is ready to operate after the power supply (AC, DC, or remote power)
and port and line cables are connected. However, identifications and settings
should be checked and, if required, statistics and error counter should be reset.
DNT2Mi can be configured, tested, and controlled via:
Front panel LCD and keys
Service Terminal (using Q1)
Macro Service Terminal Emulator running on a PC (using Q1).
Other Nokia management products, such as Nokia NMS, can be used for the same
purpose.
Menu structure for the front panel menus is shown in Chapter 8. Menu structure
for Q1 management is shown in Chapter 9.
The tables in Appendix A can be used to mark down information gathered during
the commissioning procedure.
Note
It can take up to 60 seconds to save the altered settings. If the power is switched
off during this time, the new settings will be lost. During the saving process, you
can use the equipment normally.
When the power is switched on, the unit performs an automatic self test, which is
used to check the most vital operational functions of the equipment.
During the power-up test, the Status LED and the Test LED are lit.
© Nokia Corporation
Nokia Proprietary and Confidential
Commissioning DNT2Mi
39 (128)

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Dnt2mi spDnt2mi mp

Table of Contents