Winco PSS20000/E Installation And Operator's Manual

Engine generator

Advertisement

PACKAGED
STANDBY
SYSTEM
INSTALLATION AND OPERATORS MANUAL
PSS20000/E
Automatic Transfer
Switch
PSS20000/E
Engine Generator
P/N 60706-151-2106-00

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the PSS20000/E and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Winco PSS20000/E

  • Page 1 PACKAGED STANDBY SYSTEM INSTALLATION AND OPERATORS MANUAL PSS20000/E Automatic Transfer Switch PSS20000/E Engine Generator P/N 60706-151-2106-00...
  • Page 2: Table Of Contents

    USING THIS MANUAL DC Schematic ATS Dimensions PSS20000 Layout Congratulations on your choice of a Winco generator set. UL ATS Wiring Diagram You have selected a high-quality, precision-engineered 12 MONTH WARRANTY generator set designed and tested to give you years of MAINTENANCE LOG satisfactory service.
  • Page 3: Guide To Product Safety

    SAFETY INFORMATION before refueling. Keep fuel containers out of reach of children. This engine generator set has been designed and Do not smoke or use open flame near the manufactured to allow safe, reliable performance. generator set or fuel tank. Poor maintenance, improper or careless use can Keep a fire extinguisher nearby and know its result in potential deadly hazards;...
  • Page 4: Basic Information

    Additional optional A.T.S. sizes are available to meet by the manufacturer of the applicable engines. specific needs. Contact your local WINCO Rep. or the INTRODUCTION AND DESCRIPTION WINCO Sales Department for a quote.
  • Page 5: Specification Table

    SPECIFICATIONS UNPACKING INSTRUCTIONS ** NOTICE ** GENERATOR When unpacking the generator set, be sure to inspect it MODEL WATTS* VOLTS AMPS* carefully for freight loss or damage. If loss or damage is PSS20000 20,000 120/240 83.0 3600 noted at the time of delivery, require that the person PSS20000-4 20,000 120/208...
  • Page 6: Engine Generator Installation

    INSTALLATION FUEL INSTALLATION NOTE: All PSS20000 units are tested on Natural Gas General Information and shippped configured for Natural Gas. See page 6 for conversion to LP ************* ***** WARNING **** The fuel supply should be as close as possible to the ************* engine.
  • Page 7: Vapor Fuel Pressure Tables

    voir. This is also true for the single dual stage regula- TWO (2) REGULATOR FUEL SYSTEM tors, they should also be minimum of 10 feet from the unit. If this is not done the demand regulator on the unit Supply Primary Secondary Generator...
  • Page 8: Liquid Withdrawal

    LP LIQUID WITHDRAWAL FUEL TYPE CONVERSION If it should be necessary to change the type of fuel used The following is a block diagram of a typical L/P Liquid after a unit is received, the following procedures are Withdrawal fuel system for the PSS20000. provided.
  • Page 9: Lubrication

    CONNECTING THE BATTERY CHARGER & *****NOTE***** EQUIPMENT DAMAGE- The standard NON-UL Winco BLOCKHEATER ATS does not protect against undervoltage. If you are in The battery tender and frost plug heater require a an area that is suspectible to brown outs (low voltage)
  • Page 10: Ac Electrical Connections

    ************* ***** WARNING ***** ************* FIGURE 3 All wiring must be done by a licensed electrician, and Full System must conform to the national electrical code and comply Single Phase with all state and local codes and regulations. Check with your electrical inspectors before proceeding! The standard Non-UL Automatic Transfer Switch shipped with the PSS20000 system has a 230 Amp line...
  • Page 11 PSS20000 Three Phase (FIGURE 5) FIGURE 5 The three phase units are installed the same as the FULL SYSTEM single phase units above, except a third power lead is THREE PHASE added, (i.e. a G2 from the generator, L2 on the line side and a T2 on the load side).
  • Page 12: Dc Electrical Connections

    Never run the AC and DC wiring in the same conduit. 1. Position the top right hand (RUN) slide switch to the right hand position. WINCO NON-UL ATS 2. Position the top left hand (AUTO) slide switch to the center position.
  • Page 13: Initial Start-Up

    voltage should also be checked between the hot termi- The relay in the clock will not work unless the transfer nals (G1 and G3) and the G-N to be certain of a balanced switch is installed and powered up. The relay needs 120 voltage output and a solid neutral connection.
  • Page 14: Troubleshooting Information

    TROUBLESHOOTING TABLES ENGINE WILL NOT COME UP TO SPEED AFTER IT STARTS. UNIT WILL NOT CRANK WHEN THE Insufficient fuel volume getting to the unit. POWER FAILS. Fuel line too small. Fuel pressure to low. Alarm light on from previous run cycle. Fuel load block needs to be adjusted.
  • Page 15: Preventive Maintenance

    PREVENTIVE MAINTENANCE Reasonable care in preventive maintenance will insure high reliability and a long life for the engine generator set and the Automatic Transfer Switch. ************* ***** WARNING **** ************* When performing any type of maintenance on this equipment make sure the selector switch on the engine generator is in the off position.
  • Page 16: Non-Ul Ats Wiring Diagram

    110/60ATS-3/C 230/150ATS-3/C NON-UL ATS SCHEMATIC 230/150ATS-4/D 230/150ATS-17/D NON-UL ATS SCHEMATIC LEGEND Line Side Contactor GTS/AUX Generator Side Auxiliary Generator Side Contactor LTS/AUX Line Side Auxiliary Start/Stop Relay Under Voltage Relay Exerciser Clock Start/Stop Switch Indicates Wire Number PAGE 14...
  • Page 17: Arm Connections

    PSS20000 AC CONNECTIONS PSS20000 AUTOMATIC VOLTAGE REGULATOR PAGE 15...
  • Page 18: Ac Schematic

    PSS20000 AC SCHEMATIC 120/240 VOLT SINGLE PHASE PAGE 16...
  • Page 19: Dc Schematic

    PSS20000 DC SCHEMATIC PAGE 17...
  • Page 20: Ats Dimensions

    NON-UL ATS PANEL OUTLINE DIMENSIONS ATS SIZE REF A REF B REF C REF D REF E 100/100 ATS 22.88” 14.00” 10.63” 28.25” 18.375” 225/100 ATS 22.88” 14.00” 10.63” 28.25” 18.375” 225/225 ATS 22.88” 14.00” 10.63” 28.25” 18.375” 400/225 ATS 28.00”...
  • Page 21: Ul Ats Wiring Diagram

    WINCO UL ATS Complete installation instructions for WINCO UL Automatic Transfer Switches are contained in the operator manual with each switch. Read the complete instructions before installing. ULATS100-3 120/240 1 Phase ULATS100-17 120/240 3 Phase ULATS100-4 120/208 3 Phase ULATS200-3 120/240 1 Phase...
  • Page 22: Month Warranty

    WINCO’s sole liability, and Purchaser’s sole remedy for a failure under this warranty, shall be limited to the repair of the product. At WINCO’s option, material found to be defective in material or workmanship under normal use and service will be repaired or replaced. For warranty service, return the product within 12 months from the date of purchase, transportation charges prepaid, to your nearest WINCO Authorized Service Center or to WINCO, Inc.
  • Page 23: Maintenance Log

    MAINTENANCE LOG DATE ITEM WORK PERFORMED...
  • Page 24 225 SOUTH CORDOVA LE CENTER, MN 56057 P/N 60706-151 2106-00 507-357-6821...