Hrp Switch Relocation - Bosch SM024 Installation, Operation And Maintenance Manual

Sm series
Table of Contents

Advertisement

SM Series Heat Pump
3. Locate the BACK left condensate drain and
remove and retain plastic plug covering the
cutout. (Figure#65)
Figure # 65
4. Reinstall the removed plastic plugs in the
original Condensate Drain Location.
5. Route the flexible plastic tube from FRONT left
corner post to BACK left. (Figure#66)
NOTE: Avoid kinking the hose and/or
creating a dip which could act as a second
internal p-trap. Double trapped drain lines
will not drain properly.
Figure # 66
6. Measure and cut the condensate drain hose to
the appropriate length.
7. Insert spring onto condensate drain hose.
Revised 02-15
8. Reinstall condensate drain plastic fitting and
bushing in its new location.(Figure#67)
Figure # 67

HRP Switch Relocation

The HRP Pump Disconnect Switch is shipped loose
inside unit E-Box, to be connected to either FRONT
right corner post or BACK right corner
post.(Figure#68)
Figure # 68
1. From the inside of the unit remove (2) wires
connected to HRP Pump Disconnect Switch.
Vertical Configurability | 21