8 Commissioning
Range
Explanation of the value and parameters
BatRes
Range for protection against deep discharge This range
can only be reached when the utility grid fails.
Minimum width of the deep-discharge protection
range / 262.02 BatResSOC
ProtRes
Range for protection in the event of deep discharge
This range can only be reached when the utility grid fails.
Lower limit of the deep-discharge protection range
for disconnection / 262.01 ProtResSOC
The following ranges result from the parameter default values:
Range
SlfCsmp
PVRes
BURes
BatRes
ProtRes
* December 21 (northern hemisphere) or June 21 (southern hemisphere)
** June 21 (northern hemisphere) or December 21 (southern hemisphere)
The following ranges result from deactivating seasonal adjustment with the default values of the parameters:
Range
SlfCsmp
PVRes
BURes
BatRes
ProtRes
Procedure for multicluster systems with battery-backup grid
With the Multicluster Box 12 (MC-Box-12.3-20) and the NA Box or Grid Connect Box, multicluster systems with
battery-backup grid can be installed (see Multicluster Box and NA Box / Grid Connect Box documentation).
• In a multicluster system with battery-backup grid, set the ranges of battery state of charge for each cluster to the
same values.
You can change the battery usage through battery-backup systems with increased self-consumption on the communication
product or Sunny Remote Control.
Procedure:
1. Log in to the communication product as Installer (see the user manual of the communication product) or switch to
expert mode on the Sunny Remote Control (see the Sunny Island operating manual).
80
SI30M-44M-60H-80H-IA-en-32
Lead-acid battery
Shortest day*
Longest day**
65% to 100%
45% to 100%
60% to 65%
40% to 45%
15% to 60%
15% to 40%
10% to 15%
10% to 15%
0% to 10%
0% to 10%
Lead-acid battery
65% to 100%
60% to 65%
15% to 60%
10% to 15%
0% to 10%
SMA Solar Technology AG
Behavior of the Sunny Island inverter
The Sunny Island switches into standby mode.
The Sunny Island starts up every two hours and
attempts to charge the battery with PV energy.
If the battery cannot be charged, the
Sunny Island switches back to standby mode.
When the utility grid is available, the
Sunny Island charges the battery with nominal
power from the utility grid.
When this range is reached, the Sunny Island
switches off in order to protect the battery.
When the utility grid is available again, the
system must be charged manually ("Charging
the Battery after Auto Power Off", see
Sunny Island operating manual).
Lithium-ion battery
Shortest day*
30% to 100%
25% to 30%
13% to 25%
3% to 13%
0% to 3%
Lithium-ion battery
30% to 100%
25% to 30%
13% to 25%
3% to 13%
0% to 3%
Longest day**
28% to 100%
23% to 28%
13% to 23%
3% to 13%
0% to 3%