Basic Post Installation Checks - Mira Advance ATL J97A Installation Manual

Mira advance atl adjustable temperature limit thermostatic 9.0 and 9.8 kw
Table of Contents

Advertisement

Basic Post Installation Checks

1. Turn on electrical
supply.
4. Start shower to test for
water flow. If a shower
drain pump is fitted, it
should also start.
7. Appliance will purge water from
heater tank for a few seconds.
Important! DO NOT isolate power
until water has stopped.
Go to section: "Commissioning".
2. Power to appliance,
check Start/Stop for
blue light.
5 secs
5. If there is no water
after 5 seconds, make
sure that appliance
has been primed.
22
3. Temperature to full
cold.
6. Push Start/Stop to
turn off appliance.
P u l s i n g l i g h t a n d
"beep" indicates that
appliance is shutting
down.