Complete Control Panel Replacement; Power Switch - Henny Penny 342 Maintenance Manual

Section 2. maintenance
Table of Contents

Advertisement

2-4. COMPLETE CONTROL
PANEL REPLACEMENT
Figure 2-9
Figure 2-10

2-5. POWER SWITCH

Figure 2-11
2-4
Should the control board become inoperative, follow these
instructions for replacing the board.
1. Remove electrical power supplied to the unit.
To avoid electrical shock or property damage, move the
power switch to OFF and disconnect main circuit
breaker, or unplug cord at wall receptacle.
2. Remove the two screws securing the control panel and lift out.
Figure 2-9.
3. Unplug the wire connectors going to the control panel.
Figure 2-10.
4. Remove transformer(s) from control panel. They must be
installed on the replacement panels.
5. Install new control panel in reverse order.
When plugging connectors onto new control panel, be sure the
connectors are inserted onto all of the pins, and that the
connectors are not forced onto the pins backwards. If not
connected properly, damage to the board could result.
1. Remove electrical power supplied to fryer.
To avoid electrical shock or property damage, move the
power switch to OFF and disconnect main circuit
breaker, or unplug cord at wall receptacle.
2. Remove control panel.
3. Label and remove wires from the switch. With test instrument
check across the terminals of the switch with switch in the on
position, and the circuit should be closed. In the off position,
the circuit should be open. If the switch checks defective,
replace by continuing with this procedure. Figure 2-11.
Model OFE/OFG/OEA/OGA-341, 342
504

Advertisement

Table of Contents
loading

Table of Contents