Testing an ISDN BRI trunk
Procedure 41

Perform procedure to test an ISDN BRI trunk DSL

Step
1
2
3

Removing the test setup

After acceptance testing has been completed and the results show the
system is operating correctly, remove the ISDN BRI terminal setup and
configure ISDN BRI equipment according to the customer configuration.
If the actual customer configuration was used to perform these tests, no
changes are needed.
Copyright © 2003-2007, Nortel Networks
.
Action
Set up the ISDN trunk test configuration to be used, as described
previously in the chapter "Set up ISDN BRI test terminals and
trunks".
Place a call across the ISDN BRI trunk.
Complete the call and hang up.
Nortel Communication Server 1000
ISDN Basic Rate Interface Installation and Commissioning
NN43001-318 01.02 Standard
Release 5.0 20 June 2007
Removing the test setup 103
—End—