Verifying Installation - 3Com LS8M1P12TEH Installation Manual

S7500 series ethernet switches
Table of Contents

Advertisement

Installation Manual
H3C S7500 Series Ethernet Switches
(1) Cabinet
Figure B-50 Cabinets installed on the raised antistatic floor
B.3.10 Verifying Installation
The following requirements must be satisfied:
The positions of the cabinets must comply with the construction design.
All the bolts used to fix support and cabinets should be installed stably. Spring
washers and flat washers should be installed correctly.
The insulation accessories between supports and cabinets must satisfy the
insulation requirements. Self-made bases are recommended to be insulated from
the ground or the cabinets.
The entire row of cabinets should be arranged closely and neatly. The vertical
deviation should be less than 3 mm (0.1 in.)
The cabinet doors at the primary walkway side should be in a straight line. The
error must be less than 5 mm (0.2 in.).
The surface of the entire row of cabinets should be on the same plane. Adjacent
cabinets should be closely arranged.
All the bolts should be fastened with spring washers and flat washers.
Make sure that no component is deformed.
Appendix B N68 Cabinet Installation
(2) Antistatic floor
B-52