9 Commissioning
3 In the menu, set Type = Automatic.
4 Select Start air purge.
5 Select OK to confirm.
Result: The air purge starts. It stops automatically
when done.
6 To stop the air purge manually:
1 Go to Stop air purge.
2 Select OK to confirm.
9.4.3

To perform an operation test run

Conditions: Make sure all operation is disabled. Go to the
Operation menu and turn off Room, Space heating/cooling and
Tank operation.
INFORMATION
The test run only applies to the additional temperature
zone.
1 Set the user permission level to Installer. See
change the user permission level" on
2 Go to [A.1]: Commissioning > Operation test
run.
3 Select a test from the list. Example: Heating.
4 Select OK to confirm.
Result: The test run starts. It stops automatically
when done (±30 min).
To stop the test run manually:
1 Go to Stop test run.
2 Select OK to confirm.
If the installation of the unit has been done correctly, the unit will
start up during test operation in the selected operation mode. During
test mode, the correct operation of the unit can be checked by
monitoring its leaving water temperature (heating/cooling mode) and
tank temperature (domestic hot water mode).
To monitor the temperature:
1 Go to Sensors.
2 Select the temperature information.
9.4.4

To perform an actuator test run

Conditions: Make sure all operation is disabled. Go to the
Operation menu and turn off Room, Space heating/cooling and
Tank operation.
Purpose of the actuator test run is to confirm the operation of the
different actuators (e.g., when you select Pump, a test run of the
pump will start).
1 Set the user permission level to Installer. See
change the user permission level" on
2 Go to [A.2]: Commissioning > Actuator test run.
3 Select a test from the list. Example: Pump.
4 Select OK to confirm.
Result: The actuator test run starts. It stops
automatically when done (±30 min).
To stop the test run manually:
1 Go to Stop test run.
2 Select OK to confirm.
Possible actuator test runs
▪ Backup heater 1 test
▪ Backup heater 2 test
Installer reference guide
74
"To
page 44.
"To
page 44.
▪ Pump test
INFORMATION
Make sure that all air is purged before executing the test
run. Also avoid disturbances in the water circuit during the
test run.
▪ Shut off valve test
▪ Diverter valve test
▪ Bivalent signal test
▪ Alarm output test
▪ C/H signal test
▪ DHW pump test
9.4.5

Underfloor heating screed dryout

This function is used for drying out the screed of an underfloor
heating system very slowly during the construction of a house. It
allows the installer to program and execute this program.
Conditions: Make sure all operation is disabled. Go to the
Operation menu and turn off Room, Space heating/cooling and
Tank operation.
This function can be executed without finishing the outdoor
installation. In this case, the backup heater will perform the screed
dryout and supply the leaving water without heat pump operation.
When no outdoor unit is installed yet, then connect the main power
supply cable to the indoor unit via X2M/30 and X2M/31. See
"7.9.8 To connect the main power supply" on
INFORMATION
▪ If Emergency is set to Manual ([9.5]=0), and the unit is
triggered to start emergency operation, the user
interface will ask confirmation before starting. The
underfloor heating screed dryout function is active even
if the user does NOT confirm emergency operation.
▪ During underfloor heating screed dryout, pump speed
limitation [9‑0D] is NOT applicable.
NOTICE
The installer is responsible for:
▪ contacting the screed manufacturer for the initial
heating instructions to avoid cracking the screed,
▪ programming the underfloor heating screed dryout
schedule according to the above instruction of the
screed manufacturer,
▪ checking the proper functioning of the setup on a
regular basis,
▪ selecting the correct program complying with the type
of the used screed of the floor.
NOTICE
To perform an underfloor heating screed dryout, room frost
protection needs to be disabled ([2‑06]=0). By default, it is
enabled ([2‑06]=1). However, due to the "installer-on-site"
mode (see "Commissioning"), room frost protection will be
automatically disabled for 36 hours after the first power-on.
If the screed dryout still needs to be performed after the
first 36 hours of power-on, manually disable room frost
protection by setting [2‑06] to "0", and KEEP it disabled
until the screed dryout has finished. Ignoring this notice will
result in cracking of the screed.
ERGA04~08DAV3(A) + EHVZ04+08S18+23DA +
page 40.
EHVZ04+08S18+23DJ
Daikin Altherma 3 R F
4P495249-1B – 2019.06