7.2 Checklists for commissioning

7.2
Checklists for commissioning
Note
Required checks
The lists below do not purport to be complete. It may be necessary to perform additional checks
and tests in accordance with the situation specific to the particular installation site.
Before commissioning the system, check that it is properly installed and connected.
Commission the drive system according to the Operating Instructions of the converter or
inverter being used.
Checklists for commissioning the motors 1FK2 and 1FT2
Thoroughly familiarize yourself with the safety instructions and observe the checklists below
before starting any work.
Table 7-1
Are all of the necessary components of the configured drive line-up available, correctly
dimensioned, installed and connected?
Is the manufacturer documentation for the system components (e.g. drive system, brake)
available?
Is the motor type to be commissioned known?
(e.g. 1FK2 _ _ _ – _ _ _ _ _ – _ _ _ _)
Are the ambient conditions in the permissible range?
Table 7-2
Have all touch protection measures for moving and live parts been fitted and are they
functional?
Has the motor been correctly mounted and aligned?
Can you rotate the rotor without it touching the stator?
Have all fixing screws, connecting elements, and electrical connections been tightened
with the prescribed torques and properly attached?
Do the operating conditions correspond to the data specified on the rating plate?
Do the output elements have the correct setting conditions according to type?
Examples:
84
Checklist (1) - general checks
Checklist (2) - checks regarding the mechanical system
Have the couplings been aligned and balanced?
Has the belt drive tension been correctly adjusted?
Have the gear tooth flank and gear tooth tip play as well as radial play been correctly
adjusted for geared outputs?
Check
Check
SIMOTICS S-1FK2 synchronous motors for SINAMICS S120
Operating Instructions, 02/2022, A5E46089564B AD
OK
OK

Advertisement

Table of Contents
loading

This manual is also suitable for:

Simotics s-1ft2

Table of Contents