Commissioning

Chapter 6: Commissioning

After all system components are installed, check the system for visible
damage. Check the connections in the cabinet as well.
Switch the power supply on to start up the systems. The operating
status of the system is indicated by the LED status indicator on the
back of the base unit.
- The SYSTEM LED on the back of the base unit illuminates orange,
while the system is starting up.
- The SYSTEM LED illuminates green, when the system is ready for
operation.