OPERATOR MANUAL
Replenishment Solutions
Mixing the Chemicals
Warning
Wear rubber gloves, safety glasses, and protective clothing when mixing chemicals and filling the tanks.
Important
• When mixing chemical solutions, follow all instructions and precautions on the labels of the chemical bottles.
• Mix only a 2-week supply of developer replenishment.
[1] Following all directions provided with the chemicals, mix at least 19 litres (5 gallons) of replenishment
solution.
[2] Before adding fresh chemicals to an empty processor, check that the developer and fixer Drain Valves are fully
closed. The Drain Valve Knobs should be rotated
Figure 4 Closing the Drain Valves
8
Display
Panel
1
/
turn.
4
Drain Valves
Feed Tray
H130_0019BCH
H130_0019BA
September 1995 – 981089