Fitting A Vertical Flue System; Plume Management Kit - Daikin Altherma R Hybrid Installer's Reference Manual

Hide thumbs Also See for Altherma R Hybrid:
Table of Contents

Advertisement

7.12.9 Fitting a vertical flue system

7.12.10 Plume management kit

CHYHBH05+08AF + EHYKOMB33A
Daikin Altherma R Hybrid
4P471761-1E – 2020.10
CAUTION
Read the installation manuals of the field supplied parts.
The horizontal flue MUST be installed under a 3° fall towards the boiler (50 mm per
metre) and MUST be supported with a minimum of 1 bracket at each meter length.
Best recommended position of the bracket is just before the joint.
INFORMATION
Flexible flue gas lines may NOT be used in horizontal connection sections.
A vertical 60/100  mm flue kit is also available. By using additional components
available from your boiler supplier, the kit can be extended up to a maximum
length as specified in the table indicating the maximum pipe lengths (excluding the
initial boiler connection).
CAUTION
Read the installation manuals of the field supplied parts.
See the local and national regulations.
Especially for UK:
The plume management kit comprises of a 710  mm horizontal section elbow to
connect the 500  mm vertical condensing tube, which has a horizontal or vertical
terminal dependant on your requirements. The maximum length of the horizontal
flue including the terminal but excluding the initial elbow from the boiler and
500 mm vertical condensing tube is 7 m.
7
Installation
|
Installer reference guide
97