Daikin SkyAir RZR-P Series Engineering Data page 175

Cooling only 60hz, heat pump 60hz, r-410a, inverter
Hide thumbs Also See for SkyAir RZR-P Series:
Table of Contents

Advertisement

Installation of indoor unit
Remove the drain plug, the insulation tube, and the drain hose from the drain pan and replace.
(Refer to Fig. 8)
Connect the local refrigerant piping ahead of time, matching it to the liquid pipe and gas pipe marks en-
graved on the installation panel (accessory) (1).
< Replacing the drain hose and drain plug >
(1) Remove the drain plug and insulation tube.
(2) Remove the drain hose and replace onto the left side.
(3) Replace the drain plug and the insulation tube onto the right side.
Insulating tube
Make sure
there are
no gaps.
Fig. 8
(6)
Hook the indoor unit onto the installation panel. (Refer to Fig. 9)
Placing buffering material between the wall and the indoor unit at this time will make work easier.
Front panel
Be sure to pass all wires through
the wiring guide.
Refrigerant piping
Wiring (locally procured)
Transmission wiring, Remote controller wiring
For bottom-right and back-right piping
Pass the drain hose and the refrigerant piping to the wall.
(7)
Pass power supply wiring and ground wiring threaded through conduit (For connecting the con-
duit to the unit, see "8-1 HOW TO CONNECT WIRINGS"), and remote controller wiring through the
wiring guide in through the back of the indoor unit and to the front.
9
174
Drain plug
Do not place lubricant (refrigerant oil) when inserting.
This may cause deterioration and water leaks.
Insert using a hexagon wrench (4mm).
Service lid
Hook the indoor unit hook onto the installation panel (1).
Front grill
Tab
(There are 2 places.)
Place buffering material
Wall
Power supply wiring,
Ground wiring
Conduit
Installation panel
(accessory) (1)
Fig. 9
EDUS281120_a
English
3PN07521-2C
RZR-P, RZQ-P(9)

Hide quick links:

Advertisement

Table of Contents
loading