Siemens SIMATIC ET 200pro Series Operating Instructions Manual page 88

Low voltage converter for the distributed i/o system
Hide thumbs Also See for SIMATIC ET 200pro Series:
Table of Contents

Advertisement

Commissioning
6.6 Basic commissioning
4. Switch on the motor.
The inverter starts the motor data identification. This measurement can take several
minutes.
Depending on the setting, after motor data identification has been completed, the inverter
switches off the motor - or it accelerates it to the currently set setpoint.
5. If required, switch off the motor.
6. Relinquish the master control after the motor data identification.
7. Press button
You have completed the motor data identification.
Self-optimization of the speed control
If you have selected not only motor data identification but also rotating measurement with
self-optimization of the speed control, you must switch on the motor again as described
above and wait for the optimization run to finish.
88
(RAM to ROM).
Operating Instructions, 09/2017, FW V4.7 SP9, A5E34257324B AE
SIMATIC ET 200pro FC-2 converter