Acceptance test of the inverter
The acceptance test of the inverter is a part of the acceptance test of the entire machine or
plant.
The acceptance test of the inverter checks whether the integrated drive safety functions are
set up correctly for the planned safety function of the machine.
Documentation of the inverter
The following must be documented for the inverter:
● The results of the acceptance test.
● The settings of the integrated drive safety functions.
The STARTER commissioning tool logs the settings of the integrated drive functions, if
necessary.
The documentation must be signed.
Who may perform the acceptance test of the inverter?
Personnel from the machine manufacturer, who, on account of their technical qualifications
and knowledge of the safety functions, are in a position to perform the acceptance test in the
correct manner are authorized to perform the acceptance testing of the inverter.
SIMATIC ET 200pro FC-2 converter
Operating Instructions, 09/2017, FW V4.7 SP9, A5E34257324B AE
Recommended acceptance test (Page 257)
Documents for acceptance (Page 122)
Advanced commissioning
7.7 Safe Torque Off (STO) safety function