This section provides information for connecting the AC and DC conductors and
the ground conductors. Table A-5, Table A-6, and Table A-7 on page A–5 show
the specifications of the AC and DC wiring.
To connect the AC utility to AC Interface:
1. Open the door to the AC Interface.
2. Connect the AC power conductors at the TB1-A (A phase), TB1-B (B phase),
and TB1-C (C phase) terminals using the M10 hardware. Cables to these
terminals must use a crimp-on type ring terminal or compression-type lug.
See Figure 3-9 for the location of these terminals.
3. Terminations for the neutral (TB1-N) and ground (TB2) conductors within the
AC Interface at the groundbar are made with 10 mm hardware. Cables to
these terminals must use a crimp-on type ring terminal or compression-type
lug. See Figure 3-8 on page 3–11 and Figure 3-9 on page 3–13 for the location
of these terminals.
4. Close the door to the AC Interface.
To connect the Auxiliary Control Interface within the AC Interface:
1. Open the door to the AC Interface and remove the factory-installed jumpers.
2. Route the Auxiliary Control Interface conductors through the conduit from
the source to the AC Interface.
3. Connect the ACAuxiliary Control Interface conductors at the TB7 terminal
block. These conductors must use crimp-on type ring terminals or
compression-type lugs. See Figure 3-10 for the location of these terminals.
4. Close the door to the AC Interface.
This manual for use by qualified installers only
153379

Advertisement

Table of Contents
loading

This manual is also suitable for:

Gt100-480-ngGt100-480-pgGt100-208-pgGt100-208-ng

Table of Contents