Mounting and Anchoring the Units

153379
To mount and anchor the GT100:
1. Predrill the floor or pad to accept ACI 355.2-approved masonry anchors, or
ensure it has pre-installed anchoring bolts that will fit the 19 mm (0.75 in)
mounting holes.
Note:
Alternatively, the GT100 can be installed or placed into
position, and drilled afterwards for anchoring the enclosure. See
Figure 2-4 on page 2–8.
2. Lift the GT100 from beneath with a forklift or above with a sling as shown in
Figure 3-2 on page 3–4 and Figure 3-3 on page 3–4. Move the Enclosure into
place.
3. Secure the Enclosure base to the floor with the appropriate anchoring
hardware.
4. Install the skirts to the base of the GT100 using the M5 hardware provided.
Note:
The solid skirt is to be replaced at the rear of the GT100
enclosure base, and the perforated skirt is to be replaced at the
front of the GT100 enclosure base.
This manual for use by qualified installers only
Mounting and Anchoring the Units
3–7