Planning

Anchoring the GT100

4X Ø 19 mm
(0.75 in)

Figure 2-4 Main Inverter Anchor Bolt Pattern, Bottom View

2–8
The GT100 must be anchored to a level concrete floor or pad in accordance with
ASCE 7 -05. The concrete floor or pad, upon which the GT100 is anchored, must
be structurally designed to meet any local, state, or national requirements for
weight, seismic, and wind sheer if applicable.
Four 19 mm (0.75 in) holes are provided in the feet of the Enclosure for anchoring
to the floor or pad. The floor or pad may be pre-drilled to accept ACI 355.2
approved masonry anchors or have pre-installed anchoring bolts. Alternatively,
the GT100 can be installed or placed into position, and drilled afterwards for
anchoring the enclosure.
Figure 2-4 below depicts the layout pattern of the anchoring holes for the GT100
inverter assembly.
This manual for use by qualified installers only
1518 mm
(59.75 in)
457 mm
530 mm
(18.00 in)
(20.88 in)
89 mm
(3.50 in)
74 mm
(2.93 in)
76 mm
(3.00 in)
305 mm
(12.00 in)
381 mm
(15.00 in)
305 mm
(12.00 in)