Commissioning; Measures Prior To Commissioning - Siemens SIMOTICS A-1FV5 Operating Instructions Manual

Synchronious/induction motors
Table of Contents

Advertisement

Commissioning

7.1

Measures prior to commissioning

Before commissioning the system, check that it is properly installed and connected. The
drive system must be commissioned as described in the operating instructions for the
converter/inverter.
Note
This list below does not claim to be complete. It may be necessary to perform additional
checks and tests in accordance with the specific, on-site situation.
Thermal hazard: hot surfaces
The surface temperature of the motors can exceed 65 °C.
Do not touch hot surfaces.
If necessary, implement shock-hazard protection measures.
Temperature-sensitive parts (electric cables, electronic components) must not be placed on
hot surfaces.
Mechanical connection
The following conditions must be fulfilled and suitable for the operating conditions:
● All touch protection measures for moving and live parts must have been applied.
● The motor has been assembled and aligned properly.
● The rotor must be able to be manually rotated or using suitable equipment without coming
● The operating conditions correspond to the data specified on the rating plate.
● All fixing screws, connecting elements, and electrical connections must be tightened and
● The output elements have the proper setting conditions according to type, for example.
SIMOTICS A-1FV5/1PV5 synchronous/induction motors
Operating Instructions, 03/2014, 610.45002.40
CAUTION
into contact with the stator.
properly implemented.
– Couplings are aligned and balanced.
– The belt tension is properly adjusted if a belt drive is used.
– Gear tooth flank play and gear tooth tip play as well as radial play are properly
adjusted if a gearwheel drive is used.