4.8

Test Run Checklist

Review the checklist before performing a test run. Check each item that applies.
No.
1
Thoroughly read the manual before performing a test run.
2
Turn the power on.
3
Set the voltage for the power supply to E1-01.
Check the items that correspond to the control mode being used.
WARNING! Ensure start/stop and safety circuits are wired properly and in the correct state before
energizing the drive. Failure to comply could result in death or serious injury from moving equipment. When
programmed for 3-wire control, a momentary closure on terminal S1 may cause the drive to start.
No.
V/f Control (A1-02 = 0)
Select the best V/f pattern according to the application and motor characteristics.
4
Example: If using a motor with a rated frequency of 60.0 Hz, set E1-03 to "1".
5
Perform Auto-Tuning for Energy Savings if using Energy Saving functions.
Open Loop Vector Control (A1-02 = 2)
6
Uncouple the load from the motor when performing Rotational Auto-Tuning.
7
Perform Rotational Auto-Tuning.
The following data entered during Auto-Tuning should match the information
written on the motor nameplate:
motor rated output power (kW) → T1-02
rated voltage (V) → T1-03
8
rated current (A) → T1-04
base frequency (Hz) → T1-05
number of motor poles → T1-06
motor rotations per minutes (r/min) → T1-07
PM Open Loop Vector Control (A1-02 = 5)
9
Set permanent motor parameters E5-01 through E5-24
YASKAWA ELECTRIC TOEP C710606 09B YASKAWA AC Drive V1000 Installation & Start-Up Manual
4.8 Test Run Checklist
Checklist
Checklist
Page
153
138
4
Page
139
155
153
157
160
110
171

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents