Lightning The Boiler - Biasi Riva Advance Combi Installation & Operation Instructions

Wall hung gas boiler for central heating supply
Table of Contents

Advertisement

15. Commissioning Cont.
Note: If external controls are fitted (e.g. room thermostat) ensure they "call for heat".
THE BOILER AND ITS GAS CONNECTION MUST BE LEAK TESTED BEFORE THE
• Electrically power the boiler safety. The LCD display will show the sequence in Figure 15.5.
• Turn the function selector 7 as shown in Figure 15.6.
Figure 15.5
The LCD display shows the sequence in
Figure 15.7.
45 RIVA ADVANCE COMBI MANUAL
15.4 Lighting the boiler:
WARNINGS
BOILER IS PLACED IN OPERATION
8
7
6
Figure 15.6
Figure 15.7

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents