Delta Electronics. Inc.
7.2. D-sub Operating Steps
Example : CP mode 20 kW output
Operating steps:
Set the front panel => Interface Setup => Communnication Setup => D-sub.
1.
Command Level: Set +10 V input to pin 5 for 20 kW Command.
2.
Power On: Connect pin 4 to pin 9
3.
Power Off: Remove pin4 from pin 9.
4.
7.3. RS-232 Operating Steps
Set the front panel => Interface Setup => Communnication Setup => RS-232.
1.
Follow the protocol defined in chapter 6.4 to operating.
2.
7.4. RS-485 Operating Steps
Set the front panel => Interface Setup => Communnication Setup => RS-485.
1.
Follow the protocol defined in chapter 6.4 to operating.
2.
7.5. Parallel Operating Steps
Parallel operating example 1: Two sample parallel
Operating steps:
1. Connecting set up follow chapter 5
2. Panel System Configuration Parallel Number 2
3. Parallel port 5~8 set IP position, two sample must set up different IP
Example: sample 1 set 0000, sample 2 set 0001
4. Than can follow chapter 7.1 turn on output
Parallel operating example 2: Three sample parallel
Operating steps:
1. Connecting set up follow chapter 5
2. Panel System Configuration Parallel Number 3
3. Parallel port 5~8 set IP position, two sample must set up different IP
Example: sample 1 set 0000, sample 2 set 0001,sample 3 set 0010
4. Than can follow chapter 7.1 turn on output
HPH- 20KA01KAT