Commissioning

The gas pressures of the appliance are factory preset for direct flue installations and will normally
not require adjustment.
For all Arriva flueing EXCEPT direct flueing, the appliance must be down rated as per the
instructions on the commissioning sheet. The commissioning sheet is located in a plastic pouch
behind the removable access panel on the combustion chamber glass panel, as shown below.
Follow the commissioning instructions, and ensure correct operation of the appliance.
Commissioning sheet position
Arriva 752 Installation Guide: 12218-F 06-18 | 13