Daikin AVV Installation And Maintenance Manual page 9

Classroom unit ventilators floor models digital ready, microtec control (“j” vintage) field controls by others
Hide thumbs Also See for AVV:
Table of Contents

Advertisement

Louver Installation With Typical Unit
Configurations (continued)
Unit Configuration Type AN
Note:
Arrangement AB with full metal back panel, similar to
configuration type AN. (Outside air opening to be cut and
sealed by others.)
Figure 13: 21-7/8" (556mm) Deep Full Adapter Back Unit
With Standard Louver Application
Lintel
(By Others)
Louver
Sealed Cement
Mortar; Pitch Away
From Unit
Figure 14: 21-7/8" (556mm) Deep Full Adapter Back Unit
with High Louver Application
Lintel (By Others)
Louver
Sealed Cement
Mortar; Pitch Away
From Unit
Not More Than
28"(711mm)
Important: Gasket sealing surface is required.
www.DaikinApplied.com
Piping
Piping
1"
(25mm)
Floor Line
Important: Gasket sealing
surface is required.
Piping
Piping
Floor Line
Unit Configuration Type AP
Figure 15: The 21-7/8" (556mm) Deep Full Adapter Back
Unit with Closed Pipe Tunnel, Ducted with Top Intake
Intake Louver
Important: Gasket sealing surface is required.
Unit Configuration Type AK
Figure 16: 21-7/8" (556mm) Deep Partial Adapter Back Unit
with Open Pipe Tunnel
Lintel (By Others)
Intake Louver
Not More
Than 12"
Sealed Cement
Mortar; Pitch Away
From Unit
9
Window Sash
"Goose Neck" Insulated Duct
(By Others)
Duct Collar (By Daikin)
Piping
Piping
Floor Line
Piping
Piping
Floor Line
1"
Important: Gasket sealing surface
is required.
IM 817-7

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

AvsAvbAvr

Table of Contents