Lifting & Placing
Straining or crushing injury
may occur from improperly
lifting machine or some of
its parts. To reduce this risk,
get help from other people
and use a forklift (or other
lifting equipment) rated for
weight of this machine.
The following procedure details how to place the
machine's base, and then how to lift and secure
the machine to the base.
To lift and place machine:
1.
Place
shipping
location, then remove crate from shipping
pallet and set small items aside.
2.
Unbolt base from shipping pallet.
3.
Move base to selected location and properly
anchor it to floor (refer to Anchoring to Floor
on Page 18).
4.
Remove (4) cap screws that secure electrical
box inside riser column (see Figure 6).
Electrical Box
Figure 6. Location of cap screws that secure
electrical box.
5.
Slide electrical box out of riser column and
place on top of machine.
-16-
HEAVY LIFT!
crate
near
installation
Cap
Screw
(1 of 4)
6.
Remove (4) cap screws that secure riser
column front cover (see Figure 7).
Riser
Column
Figure 7. Location of cap screws that secure
front cover.
7.
Remove (6) pre-installed cap screws, lock
washers, and flat washers from top of base
(see Figure 8).
Figure 8. Cap screws on top of base.
8.
Have another person hold machine steady so
that it does not tip, then remove hex nuts that
secure machine body to pallet.
Model G0767Z (Mfd. Since 11/17)