Configuring Inputs Bi1, Bi2, And Ui3; Configuring The Sequence Of Operation (Seqopera) - Johnson Controls TEC20x6-4 Series Installation Instructions Manual

Table of Contents

Advertisement

Note: Pressing the FAN key during configuration
restarts the list of displayed parameters at the first
parameter listed in Table 6.
When the thermostat controller is in the Installer
Configuration Menu and left unattended for
approximately 8 seconds, the thermostat controller
reverts to the Status Display Menu.

Configuring Inputs BI1, BI2, and UI3

When BI1 and BI2 are configured for an alarm
condition, an alarm condition displays locally when the
input closes. An alarm message is included on the
scrolling Status Display Menu and when the message
is displayed, the backlight momentarily lights up.
Table 4: Selection Options for Sequence of Operation in Two-Pipe Applications
Selection
Option
(0): Cooling Only
(1): Heating Only
(2): Cooling with Reheat
(3): Heating with Reheat
12
TEC20x6(H)-4 and TEC20x6H-4+PIR Series Wireless Thermostat Controllers with Dehumidification
Capability, Fan Control, and Occupancy Sensing Capability
Control
Terminal Numbers Used (See Table 2 and Figure 5.)
Curve
On/Off Control
See Figure 16.
10: Normally Open
(N.O.) Cooling
11: Normally Closed
(N.C.) Cooling
See Figure 17.
10: N.O. Heating
11: N.C. Heating
See Figure 18.
6 and 7: Reheat
10: N.O. Cooling
11: N.C. Cooling
See Figure 19.
6 and 7: Reheat
10: N.O. Heating
11: N.C. Heating
The UI3 input provides changeover of hot/cold water
switching or supply air temperature monitoring at the
thermostat controller.
Each input can be configured to the Selection Options
included in Table 6.
Configuring the Sequence of Operation
(SeqOpera)
Choose the appropriate sequence of operation. The
modes presented are user-dependent on the sequence
of operation selected. For two-pipe applications using a
changeover sensor, choose the selection option
(0): Cooling Only. Changeover occurs between
Cooling Only and Heating Only. See Figure 16
through Figure 21 for sequence of operation examples.
Floating Control
10: Open Cooling
11: Closed Cooling
10: Open Heating
11: Closed Heating
6 and 7: Reheat
10: Open Cooling
11: Closed Cooling
6 and 7: Reheat
10: Open Heating
11: Closed Heating
Proportional
0 to 10 VDC Control
10: Proportional Cooling
10: Proportional Heating
6 and 7: Reheat
10: Proportional Cooling
6 and 7: Reheat
10: Proportional Heating

Hide quick links: