J. Installing External Refractories
Open Refractory Package
•
1 - LH side refractory panel
•
1 - RH side refractory panel
•
1 - Front hearth refractory panel
Notches indicate
top of refractory
Front Hearth
Figure 12.11 Refractory Pieces
Install Side Refractories
•
Locate right side refractory panel. See Figure 12.11.
•
Install rod in hole in glass frame top. See Figure 12.12.
•
Install rod with swedge (Figure 12.13) in hole in glass
frame bottom. See Figure 12.14.
•
Repeat for the left side refractory panel.
Insert Pin
Figure 12.12 Insert Pin into Top Frame
Swedge
Figure 12.13 Swedge
(Figure 12.11)
Right
Left
Notch
Heatilator • ICON DV • 4042-300 Rev R • 06/07
Insert Pin
Figure 12.14 Insert Pin into Bottom Frame
Bottom Front Hearth Refractory
•
Slide hearth refractory under side refractories until tight
against glass. See Figure 12.15.
Figure 12.15 Placing Bottom Front Hearth Refractory
Figure 12.16 Finished Refractory Installation
Swedge
39