Fitting The Ventilation Air Unit; Checking For Leaks During Operation; Checking The Ionisation Current; Completing Inspection And Maintenance - Buderus Logano plus GB402 Installation And Maintenance Instructions Manual

Table of Contents

Advertisement

9.9.5

Fitting the ventilation air unit

NOTICE: System damage through
contaminated air.
B Prior to fitting the ventilation air hose,
check the ventilation air grille (integrated
into the lower hose adaptor) for
contamination and clean if required.
B Push on the ventilation air hose together with the
connector onto the ventilation air collector and secure
with a hose clip at the upper adaptor.

9.10 Checking for leaks during operation

NOTICE: Risk of system damage due to
short circuit.
B Cover the fan and other areas at risk prior
to commencing the leak detection.
B Never spray the leak detection agent on
cable entries, plugs or cables. Do not allow
it to drip onto them either.
B Start the boiler and check all gaskets for leaks under
full load using a leak detection agent.
B For further leak checks of the entire gas train, see
Chapter 7.15, page 36.

9.11 Checking the ionisation current

To ensure trouble-free operation, the ionisation current at
partial and full load (and burning flame) should be at least
15 μA.
The ionisation current (flame current) can be read off on
the RC35 programming unit at "SERVICE MENU
DIAGNOSIS/MONITOR VALUE" (
9.12 Completing inspection and
maintenance
9.12.1 Removing meters
Observe the instructions for the BC10 and
RC35.
9.12.2 Installing casing parts
B Fit the casing parts (
9.12.3 Confirming inspection and service
B Sign the inspection and maintenance report in this
manual (
Chapter 9.14).
Logano plus GB402 - Subject to technical modifications!
Chapter 7.14.1).
Fig. 37, page 37).
Inspection and maintenance
9.13 Replacing the gaskets subject to
time in use
The following gaskets must be replaced after expiry of the
specified time in use.
Gasket
Mixture manifold
gasket (O-ring)
Cleaning cover
gasket (on the heat
exchanger)
Tab. 15 Replacement according to time in use
1) Applicable to all conventional uses of the boiler as a gas
condensing boiler for DHW and central heating.
2) Applicable to use of the boiler for industrial heat generation with
constantly high flow temperatures and burner loads, for
example.
WARNING: Risk to life from escaping gases!
B Always replace the electrode block gasket
when replacing electrodes.
B During every service, replace the gasket at
the gas connection flange of the gas valve.
B Generally, replace damaged gaskets or
ones that appear aged.
We recommend the replacement of the
electrode block as part of the annual service.
Replacement after x years
in use for type of use:
1)
Standard
Industrial
after
after
5 years
3 years
9
2)
51