Inspection And Maintenance; Preparing The Boiler For Servicing; General Work - Buderus Logano plus GB402 Installation And Maintenance Instructions Manual

Table of Contents

Advertisement

9

Inspection and maintenance

9
Inspection and maintenance
Heating systems should be regularly serviced for the
following reasons:
• to maintain a high level of efficiency and to operate the
system economically (low fuel consumption),
• to achieve a high level of operational reliability,
• to maintain the cleanest possible combustion,
• to ensure reliable operation and long service life.
Maintenance must only be carried out by qualified service
engineers. If parts are replaced, use exclusively Buderus-
approved components. A service must be carried out
once a year. The results of the services must be recorded
in the inspection and maintenance report.
Offer your customer an annual contract covering
inspection and demand-dependent service. The work that
needs to be included in a maintenance contract is
detailed in the inspection and maintenance reports
(
Chapter 9.14, page 52).
Spare parts can be ordered from the
Buderus spare parts service.
9.1

Preparing the boiler for servicing

DANGER: Risk to life from electric shock!
B Prior to opening the boiler:
Disconnect the power across all poles and
secure against unintentional reconnection.
B Shut down the heating system.
B Undo the locking screw from the top centre of the
boiler front panel.
B Slightly lift the front panel and remove by pulling
forwards.
DANGER: Risk to life from explosion of
flammable gases!
B Only registered gas fitters are permitted to
carry out work on gas lines (observe local
regulations).
40
Fig. 39 Removing the front panel
1
Front
9.2

General work

The following work is not described in any further detail in
this document. It must, nevertheless, still be carried out:
B Check the general condition of the heating system.
B Visual inspection and function check of the heating
system.
B Check the balanced flue routing for function and safety.
B Check all gas and water pipes for signs of corrosion.
B Replace any corroded lines.
B Check the pre-charge pressure of the diaphragm
expansion vessel.
B Check the concentration of any anti-freeze/additives
that may be used in the system fill/top-up water
annually.
Logano plus GB402 - Subject to technical modifications!