7.1 General
• Use piping materials and joining methods acceptable
to authority having jurisdiction. In absence of such
requirements:
• USA - National Fuel Gas Code, ANSI Z223.1/NFPA 54
• Canada - Natural Gas and Propane Installation Code,
CAN/CSA B149.1
• Size and install gas piping system to provide suffi cient
gas supply to meet maximum input at not less than
minimum supply pressure. See Table 5.
• Support piping with hooks straps, bands, brackets,
hangers, or building structure components to prevent or
dampen excessive vibrations and prevent strain on gas
connection. Boiler will not support piping weight.
• Use thread (joint) compound (pipe dope) suitable for
liquefi ed petroleum gas.
• Provide sediment trap up stream of gas valve.
• Install manual main shutoff valve outside of jacket. See
fi gure 16.
7.2 Conversion To LP
Refer to Gas Conversion Kit Instructions.
DANGER
Fire Hazard. Do not use matches, candles, open
fl ames, or other methods providing ignition source.
Failure to comply will result in death or serious
injury.
7.3 Leak Check Gas Piping
Pressure test boiler and gas connection before placing
boiler in operation.
• Pressure test over 1/2 psig (3.5 kPa). Disconnect
boiler and its individual gas shutoff valve from gas
supply system.
• Pressure test at 1/2 psig (3.5 kPa) or less. Isolate
boiler from gas supply system by closing manual gas
shutoff valve. See fi gure 16.
• Locate leakage using gas detector, noncorrosive
detection fl uid, or other leak detection method
acceptable to authority having jurisdiction. Do not use
matches, candles, open fl ames, or other methods that
can provide ignition source.
• Correct leaks immediately and retest.

7 - GAS SUPPLY PIPING

Figure 15 Manual Main Gas Shutoff Valve
With Manufacturer Suggested Piping With Drip Leg
Nipple
¾" x 3" NPT
Tee ¾" NPT
Nipple ¾ x
3" NPT
¾" Pipe Cap
Manufacturer suggested gas piping with drip leg.
Table 5 - Gas Supply Pressure
22
Outside Boiler Jacket
Gas Supply Pressure
Natural Gas
Min.
Max.
3.5" w.c.
14" w.c. (3.3
(0.7 kPa)
kPa)
Gas
Connection
¾" Gas
Nipple
Shutoff
¾ x 3"
Valve in ON
Postion
NPT