ON-SITE ......................8 CONFIRMING CORRECT OPERATION ...............9 THE PHASER ......................10 USING PULSE INPUT DEVICES .................11 DOWNLOADING DATA ..................12 TROUBLESHOOTING...................13 TECHNICAL INFORMATION ................14 SPECIFICATION ....................15 WORKING CONDITIONS..................16 MAINTENANCE AND CLEANING CONDITIONS..........16 CONNECTIONS......................17 CE MARKING......................18 LOW VOLTAGE DIRECTIVE................18 GLOSSARY ......................19 KANE INTERNATIONAL LIMITED...
HAWK 5000 OPERATOR MANUAL GENERAL INFORMATION This is the section, which gives you an introduction to the HAWK5000 system and its hardware. It will make the subsequent operation easier to understand if you read through this first. Software operations are separately described in the Hawk Commander and Hawk Reporter Professional text files.
Page 4
The HAWK measures mains voltage and frequency from its mains supply. The other two phases of a three-phase system are assumed to have the same amplitude, waveform and frequency, but to be 120 degrees apart. The HAWK5000 does not require any connections to live bare conductors. KANE INTERNATIONAL LIMITED...
HAWK 5000 OPERATOR MANUAL Range of measurements... HAWK5000 is capable of measuring any or all of the following: Current x 3 phases Power x 3 phases x 3 phases Total Reactive power x 3 phases Lagging reactive power x 3 phases...
At the time of updating this manual Kane International Ltd is not aware of any field based situation where such interference has ever occurred and this advice is only given to satisfy the requirements of the Directive.
HAWK 5000 OPERATOR MANUAL GETTING STARTED WITH THE HAWK5000 OVERVIEW The operations required to perform a survey are: a) Connect the HAWK to a PC and run the Commander or Hawk Reporter Professional program. b) Enter the SET-UP section of the program.
Assuming that the HAWK has previously been set up, and you are now at the site to be surveyed: If you can arrange to have a portable computer with you, the HAWK5000 software and a suitable serial lead, this will allow you to verify correct operation, and also to change the set-up, or start a new survey if necessary.
CT, or connecting the one offending CT the other way around on the cable. 4. When none of the three green CT lights are flashing, all connections are correct. 5. The values being measured may be viewed by connecting a portable computer to the HAWK. KANE INTERNATIONAL LIMITED...
(PP3 type) battery. Since it is used very infrequently for short periods the battery should last for many years. If the battery does require replacing access can be obtained by removing the two screws that hold the case together. KANE INTERNATIONAL LIMITED...
+12V DC power out pin. Note that this power output is unregulated, and so can rise well above 12 Volts. Up to a total of 100 milliamps may be drawn from the two pulse connector power out pins. KANE INTERNATIONAL LIMITED...
Back at the office, connect the mains cable to the HAWK, and switch on. Connect the serial cable between the HAWK and the PC. Run the HAWK5000 control program on the PC, and download the stored data. KANE INTERNATIONAL LIMITED...
Click SCAN NOW to try to re-establish communication Starting a survey : Logging light doesn't flash A new survey has not been started: Use HAWK5000 control program to start a new survey. Start time not yet reached: Use HAWK5000 control program to change start time.
Page 14
Some or all data is zero: Are either of the input scale factors zero? Were any or all of the CT clamps connected incorrectly? Try using survey OVERVIEW to check that all the data really is zero. KANE INTERNATIONAL LIMITED...
1000 kW Resolution 0. 1% Accuracy 1, 3 Notes: Excludes CT accuracy With 1000: 1 CTs Assumes all three voltages are equal and equispaced Exceeds the range over which the HAWK will function Reduced accuracy below this range KANE INTERNATIONAL LIMITED...
Clean the handle and casing with a cloth moistened with a light detergent, use a cloth slightly moistened with clean water to remove residues. Dry with clean soft cloth, never expose the clamp to running water. After cleaning leave overnight in a warm room to ensure that all moisture evaporates. KANE INTERNATIONAL LIMITED...
1 Low frequency input 2 Ground 3 High frequency input 4 +12V DC power out 5 Not connected The current transformer input connections are: 1 AC current in 2 aux. 3 AC current return 4 +V aux. 5 -V aux. KANE INTERNATIONAL LIMITED...
Maximum relative humidity 80% for temperatures up to 31°C decreasing linearly to 50%RH at 40°C Mains supply 180-260V AC Inputs and connections other than the mains voltage supply should not exceed 30V rms and 42.4 V peak or 60 V DC. KANE INTERNATIONAL LIMITED...
The value stored is the average of all the measurements taken during the last logging period. Measurement period: The time between making a measurement of inputs (e.g. every 3 seconds). Sample rate: The rate at which individual instantaneous samples of the input are taken (e.g. 10,000 per second) during a measurement. KANE INTERNATIONAL LIMITED...
Need help?
Do you have a question about the Hawk5000 and is the answer not in the manual?
Questions and answers