Installation and commissioning
8
Connecting the plug-in connections and earth cable
.01.06
8
Commissioning the machine
.02
8
Switching the machine on/off
.03
8 - 6
Fig. 8 - 05
Connect all plugs as labelled in the control box.
Screw the earth cable from the machine and the main switch to earth point A.
Connect earth point A and earth point B with an earth cable.
Screw the earth cable of plug 1 to earth point B.
Clean the machine thoroughly.
Check the oil level, see Chapter 12 Care and Maintenance. . . . .
Check the machine, especially the electric wires, for any damage.
Have specialists check, whether the machine's motor can be used with the existing
mains voltage.
Switching the machine on/off, see Chapter 7.01 Main switch.
A
1
B