Rep 4.6.5 Hvps (High Voltage Power Supply) Pwb - Xerox DocuPrint P8e Service Manual

Electronic laser printer
Hide thumbs Also See for DocuPrint P8e:
Table of Contents

Advertisement

REP 4.6.5 HVPS (High Voltage Power Supply) PWB

Removal
1 Switch the printer power off and disconnect the AC power cord.
2 Remove the Face Up Cover (REP 4.1.1).
3 Remove the Print Cartridge (REP 4.5.1).
4 Remove the Front Cover (REP 4.1.2).
5 Remove the Rear Cover (REP 4.1.3).
6 Remove the Top Cover (REP 4.1.4).
7 Remove the Left Side Cover (REP 4.1.5).
8 Disconnect the following from the top of the HVPS PWB, CN2, CN3, and CN4 (Figure 4.6.5a).
9 Remove the five screws that secure the HVPS to the printer frame (Figure 4.6.5a).
10 Lower the HVPS PWB to access connector CN1. Disconnect CN1 from the HVPS PWB (Figure
4.6.5a).
NOTE: With the HVPS PWB removed, the four high voltage contacts can be removed. The three top
contacts are the same size. The bottom contact (transfer) is longer than the other three (Figure
4.6.5a).
8
Replacement
1 Assemble in reverse order.
2 Verify proper operation.
Xerox DocuPrint P8e Service Manual
These components are susceptible
to electrostatic discharge. Observe
all ESD procedures to avoid
Figure 4.6.5a. High Voltage Power Supply Removal.
9
7
CAUTION
damage.
7/98
4-31
P8e_227
Repair Procedures

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Docuprint p8ex

Table of Contents