Set DIP switches 5, 6 and/or 7 to specify function
For most Wallstations, you must also set DIP switches to specify exactly how the Wallstation is to function. Please refer to the Instructions shipped with each
Wallstation for more detailed information.
NTGRX-4S, -4S-DW, -4S-IR, -CIR, -4B Scene Selection Control
Switches 5 and 6 determine which scenes the unit will select:
Scenes 1 to 4
Scenes 5 to 8*
NTGRX-4M
Master Control
Switches 5 and 6 determine whether bottom button turns lights on or off:
ON only
* When using an Wallstation to access scenes 5—16, the scene LEDs will illuminate only on the Wallstation—not on the PRO AV DLC Control Unit.
Turn off power and wire
Review Appendix A: More About Class 2 Wiring before
proceeding!
1. Mount 1-gang U.S. wallbox*, 2 3/4 in. deep (68 mm) minimum.
2. Strip 3/8 in. (9 mm) insulation from both twisted pairs in the wallbox.
3. Connect two #18 AWG (1.0 mm
wiring (daisy-chain between stations)
4. Confirm all connections.
Control Unit
Step 4:
Start-up Procedure
Check Load Circuits.
1. Make sure the factory-installed bypass jumpers(s) are still in place between the H (Hot), and Z (zone) terminals. Replace module cover. Turn circuit breaker
on.
2. Check the input current to the Hot terminal with a "clamp-on" type current probe. The current should be no more than 16A.
3. Turn loads ON for at least 10 minutes. If circuit breaker trips, turn power OFF, then locate and correct miswire or overload.
4. Repeat the above steps until the circuit breaker does not trip.
Check Control Circuit
1. With power OFF, make sure all control wiring is correct. Replace module cover. Turn circuit breaker ON.
2. Push Buttons on Wallstation Control. The lighting should remain on full, but the control indicator lights
should go on/off.
Remove Bypass Jumpers
1. Turn power OFF.
2. Remove the load circuit bypass jumper from the control unit.
3. Turn power ON. Test the control(s) to make sure they adjust the light level. The system should now
function properly. If not, refer to the Troubleshooting section.
Scenes 9 to 12*
Scenes 13 to 16*
OFF only
2
) twisted pairs for Class 2/PELV
.
Wallstation
NTGRX-2B-SL Multi-Control
Switches 5, 6 and 7 determine the function of the unit's two buttons:
Scene 1 and Off
Scene 9/Scene 10*
Scene 13/Scene 14*
Panic Control
Mounting
Place twisted pairs in wallbox and mount as shown. Restore power.
* Some Wallstations have special mounting considerations. Please refer to
the detailed instructions supplied with each Wallstation.
† If shielded wire is used, the drain wire must also be daisy-chained. Do
not connect drain wire to earth/ground or Wallstation (unless a "D"
terminal is present).
Page 6
Fine Tuning Control
Partition Status
Zone Lockout
Sequencing
Scenes 5—16*
Bypass Jumper

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Pav6s-120Pav6s-230Pav6m-230

Table of Contents