GE LP 33 Series Operating Manual page 75

60 – 80 – 100 – 120 kva 400 vac ce / series 2
Hide thumbs Also See for LP 33 Series:
Table of Contents

Advertisement

6.
In order to discharge the DC link capacitors, insert the inverter by pressing "Inverter ON" ( I ) key.
Remark:
Command INVERTER ON will be enabled only when the inverter
voltage of each phase decreases below 7 Vac (about 30 seconds).
Before proceeding to step 7, check on the display panel that the DC
link voltage (both polarities) Vp and Vn has reached the max.
voltage of 5 Vdc (about 30 seconds).
The acoustical alarm is activated, press "MUTE" key (from Home
screen) to reset it.
7.
Disconnect the inverter by pressing "Inverter OFF" ( O ) key and hold until the LED Inverter (7)
turns OFF.
The load is now powered directly by mains through the
MANUAL BYPASS Q2.
WARNING !
If the above procedure is not completely performed, it could cause
serious damages to the UPS.
In case the procedure described on step "6 - Discharge DC link capacitors" cannot
be completely performed, the DC capacitors could be charged with dangerous
voltage for min.5 minutes.
Wait until capacitors are completely discharged before starting the UPS again.
Apart from the front door, do not open any other part of the UPS.
NOTE !
With separate mains inputs, it's possible to disconnect mains rectifier.
Modifications reserved
OPM_LPS_33E_60K_M12_2GB_V010.doc
END OF PROCEDURE
Home\Meter
INVERTER
f
:
L1
:
L2
:
L3
:
T
:
SYNCHRONISED
Home\Meter
BOOSTER
f
:
L1
:
L2
:
L3
:
Vp
:
Vn
:
Operating Manual LP 33 Series 60-80-100-120 kVA / S2
50.0 Hz
7 V
7 V
7 V
OK
50.0 Hz
397 V
395 V
393 V
5 V
5 V
Page 75/103