3.1. Case of installing two options
Please install this option (CCL001Z) on the top of options when you install two options.
Do not install under the another option.
3.2. Connection of CC-Link cable
If use other than the CC-Link dedicated cable, the performance of the CC-Link system is not
guaranteed. For the specifications and availability of the CC-Link dedicated cable, please refer
to the CC-Link catalogs.
Please use the recommended CC-Link dedicated cable after stripping the cable sheaths and
twisting the wires. If the sheath was stripped too long, the cable may contact with the adjacent
cable and cause a short circuit. If the sheath was stripped too short, the cable may be
disconnected.
Fix the communication cables after connected.
*
3.3. Wiring / Connection with the CC-Link master
The example of wiring/connection with the CC-Link master unit is shown in the following figure.
DA
CC-Link
DB
DG
Master Unit
SLD
※1
FG
As for master station, when use the Mitsubishi Electric An series, the recommended version is "LS" or
※1:
later.
Recommend screwdriver
•
Recommended tightening torque
•
Skin length
about 7mm
•
:
7mm
DA
DB
DG
SLD
FG
The example of wiring with the inverter VF-AS1
- 10 -
A small flat-blade screwdriver
:
(tip thickness 0.6mm, full length 3.5mm)
0.5 to 0.6 N・m
:
R/L1
S/L2
Inverter
T/L3
VF-AS1
CCL001Z
E6581286②
Motor
U/T1
V/T2
IM
W/T3