Physical Installation of the Receiver
2.4
The following section will guide you through the physical installation of the PRO1
receiver.
2.4.1 Rack Mounting the Receiver
The PRO1receiver has been specifically designed to fit into a 19-inch rack. There are
four screw holes provided on the front panel to directly mount the receiver in the rack.
All four screws must be in place after installing the receiver.
Caution!
2.4.2 Uneven Loading of Rack
When installing the PRO1 receiver into a rack, make sure to place heavier pieces of
equipment on the bottom and lighter pieces on the top.
Caution!
Connecting to the Satellite Dish
2.5
This section contains information required for connecting your PRO1receiver to a
satellite downlink.
2.5.1 DC Voltage Requirement
You may need to have the PRO1 receiver supply DC voltage to either an LNB or a block
down-converter (used after an LNA). If this is the case, the user must change the
receiver's LNB ON/OFF setting. If, however, you have another receiver that receives the
L-Band version of the satellite signal (950-1450MHz) then you may use a splitter with
XDS PRO1 Receiver User's Guide
X-Digital Systems
Rev A - August 29, 2009
Do not paint mounting ears as it hinders the grounding path from
the receiver to the rack.
Uneven loading may cause the rack to be unstable and
hazardous.
11
Need help?
Do you have a question about the XDS PRO1 and is the answer not in the manual?
Questions and answers