Insert Placement Requirements

The insert must be placed so that no combustibles are within, or can swing within (e.g. drapes,
doors), 36" of the front of the insert
Insert and hearth must be installed on a level, secure floor
The minimum clearances, facing, and hearth requirements in Figure 3 must be met (follow the
clearances for the type of fireplace being used - either masonry or zero-clearance).
Side
Wall
k
l
p
q

Hearth Requirements

Must extend 16" in front of the insert and 8" on both sides (min. 26" deep by 40-1/4" wide)
Must be non-combustible and at least .018" thick (26 gauge)

Masonry Fireplace Requirements

Chimney must have a clay tile liner or a stainless steel liner (positive connection)
Entire fireplace, including chimney, must be clean and undamaged. Any damage must be repaired
prior to installation of the insert
Chimney height: 15' minimum; 33' maximum.
Entire fireplace, including chimney, must meet local building requirements
© Travis Industries
n
m
x
o
(for qualified installers only)
Minimum Clearances
k
Sidewall to Insert
l
Side Facing
m
Top Facing
with mantel shield
n
Mantel to Insert
with mantel shield
o
Hearth (Front)
p
Hearth (Side)
q
Front of Insert
x
Extension onto Hearth
100-01165
9
Masonry
ZC (Metal)
Fireplace
Fireplace
15"
30"
13"
12"
28-1/2"
12"
20-1/2"
N/A
30-1/2"
24"
22-1/2"
N/A
16"
16"
8"
8"
36"
36"
10"
10"
Figure 3