These installation instructions provide all the
information needed for positioning the UPS
(including environmental requirements) and for
connecting the input and output power cables.
Inspection
Upon receiving the UPS, examine the packaging
for any signs of mishandling or damage. If any
damage is noted, call your local Liebert
representative and/or notify your carrier.
Environment
Operating in temperatures above 25° C (77° F)
will reduce battery life. The UPS environment
must be free of conductive contaminants and
excessive
moisture
flammable vapors, chemical fumes, or corrosive
gasses and liquids).
Required Setup Equipment
The tools below are required in order to properly
setup your UPS:
§
Pallet jack
§
13 mm Spanner
§
Torque Wrench (Nm)
§
Flathead Screwdriver
§
#2 Phillips Screwdriver
Preparation
(water
condensation,
Site Preparation
When deciding where to locate your UPS,
consider the weight and size of the unit. Make
sure that the structural integrity of the floor can
withstand the weight of a fully loaded unit. Refer
to the table below for size and fully populated
weight considerations:
Model
Max Weight kg
8 bay
12 bay
Check to make sure that your UPS will be
located in a well-ventilated area with at least 300
mm behind it. The UPS is force cooled with the
aid of internal cooling fans. Cooling air enters
from the front of the UPS and is exhausted
through ventilation grills in the back. It should
also have at least 1 metre in front, in order to
change modules if necessary.
The unit frame is bolted to the shipping pallet to
ensure safety. It is recommended that a pallet
jack be used to transport the unit to its operating
location (prior to unbolting the unit).
11
H x W x D mm
396
1016 x 508 x 711
539
1346 x 508 x 711
Need help?
Do you have a question about the Nfinity and is the answer not in the manual?