Chassis Final Connections
With the chassis in place, you are now ready to begin chassis
connections:
A. Move the thermostat switches to "OFF" and "AUTO". This
will keep the thermostat from cycling the chassis until final
connections are complete.
B. Connect the duct work onto the 10" collar. Plastic wire ties
(field supplied) are suggested to secure the duct work in
place. Use 2 wire ties, one for each inner and outer flex
duct sleeve.
C. Review the Final Installation Checklist before replacing the
power quick disconnect, reconnecting power to the
chassis, plugging the remote thermostat harness, or
operating the chassis.

Chassis Operation

Fresh Air Door

Low Ambient Protection

Room Freeze Protection

920-075-10
WARNING
Electrical Shock Hazard
Pull out unit's disconnect on front of the chassis
and turn off all power to unit before servicing.
Failure to do so can result in property damage,
personal injury and/or death.

Emergency Heat Override

Emergency Heat Operation

'ON'

Final Installation Checklist

'ON'.
-