Detailed Installation Steps; Typical Installation Sequence; Step 1. Framing - Lennox EDV3530CNM-B Installation Instructions Manual

Elite series edv direct-vent gas fireplaces
Table of Contents

Advertisement

WARNING
Failure to position the parts in
accordance with these diagrams
or failure to use only parts specifi-
cally approved with this appliance
may result in property damage or
personal injury.
AVERTISSEMENT
Risque de dommages ou de
blessures si les pièces ne sont
pas installées conformément à
ces schémas et ou si des pièces
autres que celles spécifiquement
approuvées avec cet appareil sont
utilisées.

DETAILED INSTALLATION STEPS

The appliance is shipped with all gas controls
and components installed and pre-wired.
1. Remove the shipping carton. Remove the
shipping pad, exposing the front glass
door.
2. Open the two latches (located under the fire-
box floor) securing the glass door. Remove
the door by tilting it outward at the bottom
and lifting it up. Set the door aside protecting
it from inadvertent damage. See Removing
Glass Panels on Page 30.
3. Remove the top louvered panel and locate
the pressure relief plates (see Figure 11).
4. Lift the pressure relief plates and remove
the cardboard from beneath each plate (be
careful not to damage the white gasket).
Pressure Relief
Plates
Remove Cardboard Before
Using Appliance
Figure 11

TYPICAL INSTALLATION SEQUENCE

The typical sequence of installation is outlined
below. However, each installation is unique
and may result in variations to the steps
described.
See the page numbers references in the follow-
ing steps for detailed procedures.
Step 1. (Page 9) Construct the appliance fram-
ing. Position the appliance within the framing
and secure with nailing brackets. Bend up
the appropriate header spacing guides for the
drywall/finish material thickness to be used
(refer to Figure 58, page 30). Bend up the
outer pair for 1/2" materials and the inner pair
for 5/8" materials. Bend out the appropriate
nailing flanges for the drywall/finish material
to be used. Nailing flanges are provided for
flush framing, 1/2 inch and 5/8 inch framing
depths (see Figure 12).
Step 2. (Page 11) Route gas supply line to
appliance location.
Step 3. Preparing the appliance vent collar.
Step 4. (Page 12) Install the vent system and
exterior termination.
Step 5. (Page 24) Field Wiring
a. Millivolt Appliances – Install the operating
control switch (not factory provided) and bring
in electrical service line for forced air-circulating
blower (optional equipment).
b. Electronic Appliances – Field wire and install
operating control switch.
Step 6. (Page 25) Install blower kit (optional
equipment).
Step 7. (Page 25) Make connection to gas
supply.
Step 8. (Page 26) Verifying appliance opera-
tion.
Step 9. (Page 27) Install the logs, decorative
volcanic stone and glowing embers.
Step 10. (Page 30) Install glass door as-
sembly.
Step 11. (Page 30) Adjust burner to ensure
proper flame appearance.
Step 12. (Page 32) Install the hoods.
Step 13. (Page 33) Attach Safety in Operation
Warnings.
Before proceeding it may be helpful to remove
the log set form the firebox and remove the
embers and volcanic stone from the control
compartment. Refer to the following steps:
1. Remove the front glass enclosure panel
(see Removing Glass Enclosure Panels on
Page 30).
NOTE: DIAGRAMS & ILLUSTRATIONS ARE NOT TO SCALE.
2. Remove log set box from firebox. Next,
remove embers and volcanic stone from con-
trol compartment. Handle logs carefully to
prevent breakage.

Step 1. FRAMING

Frame these appliances as illustrated in Figures
13 and 14 on Pages 10 and 11 (Figure 14
applies to corner framing installations only).
All framing details must allow for a minimum
clearance to combustible framing members as
shown in Table 5 on Page 8.
If the appliance is to be elevated above floor level,
a solid continuous platform must be constructed
below the appliance.
Headers may be in direct contact with the appli-
ance top spacers when they are bent up vertically
maintaining the 3" clearance to the fireplace top,
but must not be supported by them or notched
to fit around them. All construction above the
appliance must be self-supporting. DO NOT use
the appliance for structural support.
The fireplace should be secured to the side
framing members using the unit's nailing
flanges - one top and bottom on each side of
the fireplace front. See Figure 12. Use 8d nails
or their equivalent.
Unit Being Secured By Its Nailing Flanges
To The Framing
Unit Being Secured by Its Nailing
Flanges to the Framing
Figure 12 - Nailing Flanges
9