CHAPTER 6 COMMUNICATION FUNCTION

6.1.2 Operation procedure by high speed link

If master module is a product of LGIS (G3/4/6L-PUEA, G3/4/6L-PUEB), make a
configuration of Pnet by using SyCon.
Download the Pnet Configuration by master module.
Set and download the high speed link parameter of master module in GMWIN/KGLWIN.
Set 'high speed link allowable'.
If the product of other manufacturer is used as master, make a configuration of Pnet by using
a Configuration Tool of the relevant product.
Set and download the high speed link parameter of slave module in GMWIN/KGLWIN.
Convert the operation mode to RUN.

6.1.3 SyCon

If you use the master module of LGIS (G3/4/6L-PUEA, G3/4/6L-PUEB), it is required to make a
configuration of Pnet by using a SyCon and download that information to the relevant master
module. As Pnet Configuration Tool is different per master module, if you use the master module of
LGIS (G3/4/6L-PUEA, G3/4/6L-PUEB), you should use a SyCon.
Execute a SyCon as shown on Figure 6.1.
If there is no project used before, the screen like Figure 6.2 will appear. If you have been using the
project already, the latest used project will appear.
Figure 6.1 Execution of SyCon
6-2

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

G6l-puebG3l-puebG4l-pueaG4l-puebG7l-pbeaG6l-puea

Table of Contents