Install Field Insulation; Factory-Installed Insulation - Carrier 23XL Installation Instructions Manual

50/60 hz hermetic screw liquid chillers
Table of Contents

Advertisement

When connecting the CCN communication bus to a sys-
tem element, a color code system for the entire network is
recommended to simplify installation and checkout. The fol-
lowing color code is recommended:
CCN BUS CONDUCTOR
SIGNAL TYPE
INSULATION COLOR
+
Ground
If a cable with a different color scheme is selected, a simi-
lar color code should be adopted for the entire network.
At each system element, the shields of its communication
bus cables must be tied together. If the communication bus
is entirely within one building, the resulting continuous shield
must be connected to ground at only one single point. See
Fig. 31. If the communication bus cable exits from one build-
ing and enters another, the shields must be connected to ground
at the lightening suppressor in each building where the cable
enters or exits the building (one point only).
To connect the 23XL chiller to the network, proceed as
follows (Fig. 31):
1. Cut power to the PIC control center.
2. Remove the COMM1 plug from the processor module.
3. Cut a CCN wire and strip the ends of the RED, WHITE,
and BLACK conductors.
4. Using a wirenut, connect the drain wires together.
5. Insert and secure the RED wire to Terminal 1 of the
COMM1 plug.
6. Insert and secure the WHITE wire to Terminal 2 of the
COMM1 plug.
7. Insert and secure the BLACK wire to Terminal 3 of the
COMM1 plug.
8. Mount a terminal strip in a convenient location.
9. Connect the opposite ends of each conductor to separate
terminals on the terminal strip.
COMM1 PLUG
PIN NO.
Red
1
White
2
Black
3
10. Cut another CCN wire and strip the ends of the
conductors.
11. Connect the RED wire to the matching location on the
terminal strip.
12. Connect the WHITE wire to the matching location on
the terminal strip.
13. Connect the BLACK wire to the matching location on
the terminal strip.

Install Field Insulation

Protect insulation from weld heat damage and weld splat-
ter. Cover with wet canvas cover during water piping
installation.
When installing insulation at the job site, insulate the fol-
lowing components:
• compressor motor
• cooler shell
• cooler tube sheets
• suction piping
• motor cooling drain
• oil reclaim piping (Frame 1 and 2 machines only)
• cooler liquid inlet piping
• hot gas bypass piping (if applicable)
• economizer and economizer piping (if applicable)
Insulation of the waterbox covers is applied only at the
jobsite. When insulating the covers, make sure there is ac-
cess for removal of waterbox covers for servicing (Fig. 32
and 33).
Depending upon humidity conditions, field insulation of
the condenser's bottom half may be required when the ma-
chine is not operating.
FACTORY-INSTALLED INSULATION (OPTIONAL) — Op-
tional, factory-installed insulation is available for the evapo-
rator shell and tube sheets, suction pipe, compressor motor,
refrigerant lines, oil reclaim piping, hot gas bypass (if ap-
plicable), and economizer and economizer piping (if appli-
cable). The insulation is
30
3
-in. (19 mm) thick.
4

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents