Sample of an Installation Schedule

The following schedule lists the sequence of events for a typical system installation:
60 days before installation
— Floor plan design completed and mailed to HP (if required to be an HP task)
30 days before installation
— Primary power and air conditioning installation completed
— Telephone and data cables installed
— Fire protection equipment installed
— Major facility changes completed
— Special delivery requirements defined
— Site inspection survey completed
— Delivery survey completed
— A signed copy of the site inspection and delivery survey mailed to HP
— Site inspection and predelivery coordination meeting arranged with an HP representative to review
the inspection checklist and arrange an installation schedule
7 days before installation
— Final check made with an HP site preparation specialist to resolve any last minute problems
Not all installations follow a schedule like the one noted above. Sometimes, a HP 9000 rp3410
NOTE
or HP 9000 rp3440 server is purchased through another vendor, which can preclude a rigid
schedule. Other conditions could also prevent following this schedule. For those situations,
consider a milestone schedule.
Site Preparation—Schedule with the customer as soon as possible after the order is placed.
Site Verification—Schedule with the customer a minimum of one to two days before the
HP 9000 rp3410 or HP 9000 rp3440 server is scheduled to be installed.
Chapter 2
General Site Preparation Guidelines
Sample of an Installation Schedule
37

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rp3440Rp34109000 rp34109000 rp3440

Table of Contents