Sample of an Installation Schedule

The following schedule lists the sequence of events for a typical system installation:
60 days before installation
— Floor plan design completed and mailed to HP (if required to be an HP task)
30 days before installation
— Primary power and air conditioning installation completed
— Telephone and data cables installed
— Fire protection equipment installed
— Major facility changes completed
— Special delivery requirements defined
— Site inspection survey completed
— Delivery survey completed
— A signed copy of the site inspection and delivery survey mailed to HP
— Site inspection and predelivery coordination meeting arranged with a HP representative to review
the inspection checklist and arrange an installation schedule
7 days before installation
— Final check made with a HP site preparation specialist to resolve any last minute problems
Not all installations follow a schedule like the one noted above. Sometimes, a server is
NOTE
purchased through another vendor, which can preclude a rigid schedule. Other conditions could
also prevent following this schedule. For those situations, consider a milestone schedule.
Site Preparation—schedule with the customer as soon as possible after the order is placed
Site Verification—schedule with the customer a minimum of one to two days before the HP
server is scheduled to be installed
Chapter 2
General Site Preparation Guidelines
Sample of an Installation Schedule
41

Advertisement

Table of Contents
loading

This manual is also suitable for:

Rp44409000 rp4410-49000 rp4440-89000 rp44109000 rp4440

Table of Contents