DISPLAY MESSAGES
The Mini-MOD-CNC display layout reserved the second line for message indications. The following is a list of the most common
Message Display Line information:
Boost To 170˚F
The Boost has started 30 minutes before the Day Schedule setting and the Boost temperature is 170˚F.
DHW Call (180˚F)
There is a DHW call. The Mini-MOD-CNC will raise the system Set Point to the indicated temperature. DHW
increases calculated temperature to the DHW Set Point. See "DOMESTIC HOT WATER SET POINT" on page 25.
Holding Until 150˚F
The Lead boiler is in Last Stage Hold. This example shows that the lead stage will turn off when system
temperature reaches 150˚F. See "LAST STAGE HOLD" on page 34.
Lag Delay: 123
The lead boiler is at 100% and the remaining purge time to start the lag boiler in seconds is 123.
See "LAG DELAY" on page 35.
Outdoor Cutoff
The outdoor temperature is above the Outdoor Cutoff setting. No boilers will be active for heating.
Prove Failure
After boilers have run for some time, Prove signal has ended. All boilers set to Auto or Standby will
de-energize. However, the System relay will remain energized. See "PROVE/DOMESTIC HOT WATER
(DHW) PRIORITY" on page 24 and "WIRING THE PROVE" on page 14.
Purge Delay: 23
A boiler is in purge cycle and the remaining purge time in seconds is 23. See "PURGE DELAY" on page 32.
Setback to: 130˚F
The Night Schedule or Setback input is active. Current Setback temperature is 130˚F. See "SETBACK"
on page 32.
Shutdown Active
The Shutdown Terminals are Shorted. No boilers will be active. See "SHUTDOWN/TSTAT/SETBACK
MODE" on page 25 and "WIRING THE SHUTDOWN, TSTAT, OR SETBACK" on page 14.
Summer
The control is set to Summer. No heat is active. See "SEASON" on page 29.
Switch in: 00:30
The switch from one group to the other will take place after 30 minutes. See "SWITCH DELAY" on page 21.
System Run-On: 46
The System relay is ON for the System Run-On Delay. This example shows that it will remain in System
Run-On for an additional 46 seconds before turning off. See "SYSTEM RUN-ON" on page 33.
Tstat Call
The Tstat Terminals are Shorted. Boilers will be active.
Waiting for Prove
The System relay is ON and the prove terminals are open before the lead boiler relay can energize.
See "PROVE/DOMESTIC HOT WATER (DHW) PRIORITY" on page 24.
|
42
HEAT-TIMER CORP.
17 MAINTENANCE
059102-00 REV. C

Advertisement

loading
Need help?

Need help?

Do you have a question about the Mini-MOD-CNC and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

This manual is also suitable for:

Mini-extension926743-00926712-00926741-00