QUICKSTART GUIDE
E2 setup with
Carrier Corporation's
RTU open controller for 527-0359
This document will guide you through setting up and commissioning
the Carrier Corporation's RTU Open Controller in the E2 controller
(CARRIER OPN-RTUM Open Echelon device in the E2).
Note that Open Echelon description files require E2 firmware version
3.01FO1 or higher.
E2 and Echelon devices communications
network wiring diagram
Figure 1 - network wiring diagram

Advertisement

loading
Need help?

Need help?

Do you have a question about the E2 and is the answer not in the manual?

Questions and answers

Subscribe to Our Youtube Channel

Summary of Contents for Copeland E2

  • Page 1 RTU open controller for 527-0359 This document will guide you through setting up and commissioning the Carrier Corporation’s RTU Open Controller in the E2 controller (CARRIER OPN-RTUM Open Echelon device in the E2). Note that Open Echelon description files require E2 firmware version 3.01FO1 or higher.
  • Page 2 Carrier Corporation’s RTU open controller board (SW3) dip switch settings Set SW3 dip switches as shown Baud rate DS-1 DS-2 DS-3 DS-4 DS-5 DS-6 DS-7 DS-8 38.4K baud 026-4921 Rev 1 (05/2012) E2 setup with Carrier Corporation’s RTU open controller for 527-0359...
  • Page 3 3. Browse to the location of the description file and click Upload. 4. After uploading, you will need to reboot the E2 controller. Figure 3 - description file upload 026-4921 Rev 1 (05/2012) E2 setup with Carrier Corporation’s RTU open controller for 527-0359...
  • Page 4 2. Press F1 (ADD FEATURE) and enter your license key. Figure 4 -add license screen Step 3: Once the license is activated, add the device to the E2 controller. 1. Press , 7 (System Configuration), 7 (Network Setup), 2 (Connected I/O Boards & Controllers).
  • Page 5 Figure 5 - specify the number of devices to add Figure 6 - device setup screen 026-4921 Rev 1 (05/2012) E2 setup with Carrier Corporation’s RTU open controller for 527-0359...
  • Page 6 Neuron ID. Use this selection if the Neuron ID of the device is available. • 3 = Specifying a range of nodes --> The network is scanned for neuron addresses. Figure 7 - commission the device 026-4921 Rev 1 (05/2012) E2 setup with Carrier Corporation’s RTU open controller for 527-0359...
  • Page 7 Figure 8 - select method for Identifying the controller Figure 9 - identifying the controller using the neuron ID 026-4921 Rev 1 (05/2012) E2 setup with Carrier Corporation’s RTU open controller for 527-0359...
  • Page 8 NOTE: By default, any Third Party (Open Echelon) devices that are initiated in E2 will always have a generic naming sequence as shown: Example: LONMARK_001, LONMARK_002, LONMARK_003 Figure 10 - network summary screen 026-4921 Rev 1 (05/2012) E2 setup with Carrier Corporation’s RTU open controller for 527-0359...
  • Page 9 Figure 11 - Changing the device name Figure 12 - Changing the device name 026-4921 Rev 1 (05/2012) E2 setup with Carrier Corporation’s RTU open controller for 527-0359...
  • Page 10 . The device Status Screen displays. NOTE: By default, if there are one or more devices of the same type configured in E2, a list of all common devices will display (Summary Screen) in reference to the numeric or alphanumeric character sequence of the devices labeled.
  • Page 11 Figure 14 - main menu Figure 15 - configured applications 026-4921 Rev 1 (05/2012) E2 setup with Carrier Corporation’s RTU open controller for 527-0359...
  • Page 12 Figure 16 - summary screen Figure 17 - sevice status screen 026-4921 Rev 1 (05/2012) E2 setup with Carrier Corporation’s RTU open controller for 527-0359...
  • Page 13 Figure 18 - general tab Figure 19 - inputs tab 026-4921 Rev 1 (05/2012) E2 setup with Carrier Corporation’s RTU open controller for 527-0359...
  • Page 14 Figure 20 - outputs tab 026-4921 Rev 1 (05/2012) E2 setup with Carrier Corporation’s RTU open controller for 527-0359...
  • Page 15 200 million installations worldwide. Together, we create sustainable solutions that improve lives and protect the planet today and for future generations. For more information, visit copeland.com. The contents of this publication are presented for informational purposes only and they are not to be construed as warranties or guarantees, express or implied, regarding the products or services described herein or their use or applicability.