INSTALLATION, OPERATION & MAINTENANCE MANUAL R & RX SERIES TOP DISCHARGE Electric Submersible Pumps Single Phase 115V & 230V Three Phase 230V & 460V CAST IRON SINGLE PHASE THREE PHASE R100 R250 R400 R400D R400P R750 R1500 R1520 R1530 316 STAINLESS STEEL...
EXPLODED VIEW OF R08, RX08SS, R15, RX15SS ....................19 R SERIES PARTS LIST ............................... 20 RX SERIES PARTS LIST ............................22 SINGLE PHASE WIRING DIAGRAM 115V & 230V W/O GOVERNOR SWITCH ............24 MODELS R100, R250, R400 R400D, R400P ..................... 24 SINGLE PHASE WIRING DIAGRAM 115V &...
The submersible R Series pumps are designed to pump water. The RX Series pumps are designed to pump corrosive liquids in concentrations chemically compatible with 316SS and FKM. The R & RX Series pumps are not explosion- proof. They are not designed to pump volatile or flammable liquids.
SAFETY Pump installations are seldom identical. Each installation and application can vary due to many different factors. It is the owner/service mechanics responsibility to repair, service, and test to ensure that the pump integrity is not compromised according to this manual.
INSPECTION Review all safety information before servicing pump. The following are recommended installation practices/procedures for the pump. If there are questions in regards to your specific application, contact your local BJM Pumps distributor or BJM Pumps, LLC. PRE-INSTALLATION INSPECTION 1) Check the pump for damage that may have occurred during shipment.
BJM Pumps, LLC at 860-399-5937. As a general rule, R and RX Series top discharge pumps can pump down to a level above the suction screen. Pumping lower than screen will permit air to enter the pump and cavitate, lose prime or become air bound.
PUMP ROTATION Two ways to check the correct pump rotation: 1. By looking at the impeller; the rotation of the impeller should be counter clockwise as shown in the picture below. 2. By looking from the top of the pump. Since the impeller cannot be seen, the best way to check the rotation is to check the kick back motion of the pump when the pump just starts.
PUMP OPERATION This pump is designed to handle dirty water that contains some solids. It is not designed to pump volatile or flammable liquids. Do not attempt to pump any liquids which may damage the pump or endanger personnel as a result of pump failure.
STOPPING To stop the pump (manual and automatic mode), unplug it from the power source, turn off the breaker, or turn the power source off (generator). Typical 3 phase manual control 1 TYPICAL AUTOMATIC DEWATERING INSTALLATION NOTE: Maximum recommended starts should not exceed 10 times per hour. AUTOMATIC OPERATION Float switches (wired into the pump motor or piggy-back style) are available from the factory as an option.
Use with approved motor control that matches motor input in full load amperes. “UTILLISER UN DÉMARREAR APPROUVÉ CONVENANT AU COURANT Á PLEINE CHARGE DU MOTEUR.” BJM Pumps has been evaluated for use with water or water based solutions. Please contact the manufacturer for additional information. SINGLE PHASE WIRING INSTRUCTIONS...
FOR YOUR PROTECTION, ALWAYS DISCONNECT PUMP FROM ITS POWER SOURCE BEFORE HANDLING. Single phase pumps are supplied with a three prong grounded plug to help protect you against the possibility of electrical shock. DO NOT UNDER ANY CIRCUMSTANCES REMOVE THE GROUND PIN. The three prong plug must be inserted into a mating three prong grounded receptacle.
Typical 3 phase Auto Control 1 Before installing a pump, check the pump rotation to insure that wiring has been connected properly to power source, and that the green lead of power cord (See wiring diagram), is connected to a valid ground, momentarily energize the pump, observing the directions of kick back due to starting torque.
Pump should be disconnected from the electric power supply before proceeding to do any service or maintenance. To service or repair your pump, please contact your local BJM Pumps distributor. Service should only be performed by a qualified electrician. MAINTAINING YOUR PUMP ...
More frequent inspections are required if the pump is used in a harsh environment. Preventative maintenance should be performed to reduce the chance of premature failure. Worn impellers and lip seals should be replaced. Cut or cracked power cords must be replaced. (Never operate a pump with a cut, cracked or damaged power cord.) ...
BJM Pumps, LLC’s liability for any breach of this warranty shall be limited solely to replacement or repair, at the sole option of BJM Pumps, LLC, of any part or parts of the Product found to be defective during the warranty period, provided the Product is properly installed and is being used as originally intended.
START-UP REPORT FORM This form is designed to record the initial installation, and to serve as a guide for troubleshooting at a later date (if needed). BJM Pumps, LLC 123 Spencer Plain Road Old Saybrook, CT. 06475 Pump Owner’s Name...
START-UP REPORT FORM presence? Are guide rails exactly vertical? Is base elbow installed level? Liquid level controls: Model control installed away from turbulence? Operation Check Tip lowest float (stop float), all pumps should remain off. Tip second float (and stop float), one pump comes on. Tip third float (and stop float), both pumps on (alarm on simplex).
START-UP REPORT FORM Voltage supply at panel line connection, pump on L1-L2 L2-L3 L3-L1 Amperage load connection, pump on FINAL CHECK Is pump secured properly? Was pump checked for leaks? Do check valves operate properly? Flow: Does station appear to operate at proper rate? Noise level: Acceptable...