Building the Tower

2.1

Pre-Assembly Checks

Check overhead that the area into which the structure is to be erected contains
no obstructions, particularly electrical or radio radiation hazards. The structure is
conductive.
Ensure the ground on which the access tower is to be erected is capable of
supporting the tower in use.
Check the surface is level within the 210mm range of the adjustable legs.
Only components specified in this manual shall be used with BoSS towers.
Check all required components are on site and in a suitable working condition.
Damaged components shall not be used and must
be put beyond use and disposed of according to local
regulations.
Adjustable legs should only be used for levelling purposes and never to gain
extra height.
Ensure distance from the ground to first climbing rung is less than 400mm.
Only climb the tower from the inside using the access
method provided.
This tower provides a work platform. It must not be
used to access other structures.
Tower scaffolds are not designed to be lifted or suspended.
Ensure the safe working load on the structure is not exceeded.
Tools and materials should be lifted using a reliable lifting material (e.g. a strong
rope) employing a reliable knot (e.g. clove hitch) to ensure safe fastening and
always lift within the footprint of the prefabricated tower scaffold (i.e. within the
area bounded by the stabilisers).
4
5mm
BoSS Linked Tower
Instruction Manual

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Linked Tower with Bridge Platform and is the answer not in the manual?

Questions and answers

Table of Contents